L'électron rare 325fe14e5d feat: first power budget pass and physics post
Fill the power budget with argued type-values (flagged as estimates
pending nameplate readings): about 5.5 kWh on a typical workshop day,
peaks under the MultiPlus 4 kW continuous with a no-laser-plus-CNC
usage rule, 2.3 days of battery autonomy without sun, winter covered
when the deck is deployed. The system bought before the bus turns out
coherent with the workshop it will power. Blog post tells the day the
label, the datasheets and the beam equations made the decisions.
2026-07-09 14:49:13 +02:00
L'électron rare 4b4f4a3b54 feat: pre-size the sliding deck cantilever
First structural study of the awning mode, using section properties
measured on the actual C-beam STEP (I = 6.11e5 mm4 by numerical
integration). Verdict: a free cantilever fails at 80 km/h wind
(SF 0.89) while tip props turn four plain C-beams into a structure
that rides out 100 km/h at SF 2.6 — props are structural, not
optional. Baseline for the FEM stage: four C-beam crossmembers plus
two props; deployment procedure and wind fold-in rule recorded.
2026-07-09 14:23:36 +02:00
L'électron rare b3a38735d0 docs: record sliding-deck structure alternatives
Comparative survey next to the V-SLOT lead so the trade-off survives
until the FEM stage: industrial T-slot and TIG-welded aluminium for
the frame, heavy-duty telescopic slides or gate-hardware steel
rollers for the motion, and the salvage lead of a truck sliding-roof
mechanism; precision linear guides ruled out for dust and water.
2026-07-09 13:54:25 +02:00
L'électron rare 197c54e005 docs: adopt V-SLOT lead for sliding deck
The owner proposes building the roof structure in V-SLOT extrusion,
which fits the house ecosystem and makes the V-groove itself the
sliding rail. Record it as the retained lead with its three guard
rails: vibration-proofed joints, weather-protected rolling interface,
and C-beam/4080 main beams sized by FreeCAD FEM for the deployed
cantilever. Positive mechanical travel lock stays independent.
2026-07-09 13:52:47 +02:00
L'électron rare 1456a5ace3 docs: replace weight estimates with datasheet values
Official manufacturer figures for the whole energy chain: US3000C
32.0 kg (bank 128), MultiPlus 30.0, MPPT 4.5, Fronius Primo 21.5
(the one estimate that was off, +5.5 kg), Cerbo ~0.4 (reseller value,
absent from Victron docs), LONGi panel 19.5 confirmed. Weight
tracker, architecture, roof concept and the decision entry all
updated; Fronius MPP window corrected to 80-800 V.
2026-07-09 13:50:09 +02:00
L'électron rare ae1644172c docs: read panel label, settle PV string split
The LONGi label photo yields the exact model (LR4-60HPH-370M) and its
electrical figures. The voltages nearly settle the DC/AC split on
their own: ten panels in series reach 409 V, beyond the 250 V MPPT
ceiling but inside the Fronius MPP window, while the MPPT tops out at
five-panel strings. Fixed deck to MPPT as 2x5, sliding deck to
Fronius as 1x10, one conductor pair through the flexible link.
2026-07-09 13:43:57 +02:00
L'électron rare 1e4decd621 docs: estimate rooftop PV system mass
First numbered estimate for the solar roof: 20 LONGi 370 panels at
about 19.5 kg each plus fixed rails, the self-supporting sliding
frame (aluminium mandatory, steel would double it) and cabling land
around 650-700 kg. Recorded in the weight tracker and the roof
concept doc with the structural and centre-of-gravity implications.
2026-07-09 13:39:36 +02:00
L'électron rare f034fccf22 docs: add VASP regulatory research, flag blockers
Deep regulatory research (15+ official sources, RTI 03.8.3 sheet read
in full): the TCP-to-VASP procedure is nailed down (13-item dossier,
seat reduction handled inside it, 86.90 EUR), but two blocking
uncertainties surfaced. First-registration date may forbid the
conversion or require a ministerial derogation, and no firm text
covers the sliding solar deck. Both flagged as blocking questions in
parcours-vasp.md and solaire-toit.md: DREAL first, fabrication later.
2026-07-09 13:11:28 +02:00
L'électron rare 4e783cbcaa feat: draw energy synoptic on QET folio 1
Block-diagram the validated architecture as movable shapes and texts:
PV decks feeding MPPT (DC) and Fronius (AC-coupled), MultiPlus and
Pylontech bank on a highlighted 48V DC bus, P17 shore input, AC and
DC boards, Cerbo GX. Gives the electrical folios a reviewable
starting point instead of a blank page.
2026-07-09 12:59:51 +02:00
L'électron rare 0e4b7277c0 feat: seed QElectroTech project with folio plan
QElectroTech 0.100.1 is now installed locally, so the qet/ folder
gets its actual project file: five pre-named folios matching the
documented plan (synoptic, 48V DC, 230V AC, rooftop PV including the
sliding deck, monitoring/interlocks) with house title-block fields.
README updated from install instructions to open instructions.
2026-07-09 12:54:15 +02:00
L'électron rare b615968e7d docs: adopt QElectroTech for installation diagrams
Split the schematic tooling by audience: QElectroTech (IEC 60617,
versionable XML) for the 48V/230V/PV installation folios that
electricians and inspectors read, KiCad kept for in-house boards
(monitoring, solar-deck interlock). Seed qet/ with the folio plan
and conventions; record the decision.
2026-07-09 12:32:00 +02:00
L'électron rare 22fa5fcf14 docs: apply final review minor fixes 2026-07-09 11:52:01 +02:00
L'électron rare 2f7031cd2d docs: correct battery specs to US3000C 2026-07-09 11:42:21 +02:00
L'électron rare 5f0914d2ba docs: record Victron energy architecture 2026-07-09 11:21:10 +02:00
L'électron rare f808d42dde docs: seed energy and fluids domains 2026-07-09 11:04:34 +02:00