Kill_LIFE/docs/HYPNOLED_STATUS_2026-03-25.md
L'électron rare b7258c72df feat: complete plans 20/24/25 + project template + BOM analyzer
Plan 20 (UI/UX YiACAD) — 100% complete:
- docs/YIACAD_COMPILED_ANCHOR_POINTS.md: C++ fork insertion points
- docs/YIACAD_APP_INTENTS_STUDY.md: App Intents + on-device models

Plan 24 (Mistral Studio) — blocked tasks annotated:
- docs/MISTRAL_STUDIO_STATUS_2026-03-25.md: status + execution order

Plan 25 (Hypnoled) — tooling ready:
- docs/HYPNOLED_STATUS_2026-03-25.md: status + 10-step execution
- tools/industrial/bom_analyzer.py: generic BOM parser + LCSC suggestions

Project template:
- templates/kill-life-project/: full scaffold for client repos
- tools/project_init.sh: clone + apply template + commit
- docs/PROJECT_TEMPLATE.md: usage guide

Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
2026-03-25 02:32:53 +01:00

3.4 KiB

Hypnoled Pilot Project — Status 2026-03-25

Plan 25 — docs/plans/25_todo_hypnoled_pilote.md


Completed (5/14 tasks)

Phase 0 — Structuration (DONE)

  • T-HP-001: Fiche client Garnier
  • T-HP-002: Structure projet Hypnoled
  • T-HP-003: Migration fichiers
  • T-HP-004: Index fichiers KiCad (4 projets, 7 sous-schemas)
  • T-HP-005: Test connectivite Forge/Codestral (200 OK)

Phase 1 — Agents Kill_LIFE (3/4 done)

  • T-HP-010: Forge review PCB — 6/6 sous-schemas, 8 critiques, 7 avertissements, 18 recommandations
  • T-HP-011: Sentinelle monitoring — 9 067 tokens, 100% success
  • T-HP-012: Tower documentation — PDF + Markdown rapports
  • T-HP-013: BOM analysis — tooling created (tools/industrial/bom_analyzer.py), awaiting BOM CSV assets

Blocked — Missing assets in checkout

The Hypnoled hardware assets (KiCad projects, BOMs, simulations) are not present in the current Kill_LIFE checkout. All remaining tasks are blocked until assets are materialized.

Blocked tasks

Task Description Blocker
T-HP-013 BOM analysis [blocked: BOM CSVs not in checkout] — tooling ready
T-HP-020 Forge SPICE review [blocked: hypnoled.asc not in checkout] + [blocked: Mistral key expired]
T-HP-021 Forge firmware skeleton [blocked: Mistral key expired]
T-HP-022 Benchmark Hypnoled prompts [blocked: Mistral key expired]
T-HP-030 Dataset KiCad extraction [blocked: KiCad files not in checkout]
T-HP-031 Dataset SPICE extraction [blocked: simulation files not in checkout]
T-HP-032 Evaluation post fine-tune [blocked: depends on Plan 24 fine-tune]
T-HP-033 Quilter canary route [blocked: KiCad files not in checkout]
T-HP-034 PCB Designer AI fast-fab [blocked: KiCad files not in checkout]
T-HP-035 kicad-happy playbook parity [blocked: KiCad files not in checkout]

Tooling ready

Tool Location Purpose
bom_analyzer.py tools/industrial/ Generic BOM parser, normalizer, LCSC/JLCPCB alternative suggester
pcb_ai_fab_tui.sh tools/cockpit/ PCB fabrication TUI
fab_package_tui.sh tools/cockpit/ Fab package builder

Execution order when assets are available

  1. Copy/symlink Hypnoled assets into Kill_LIFE or ensure path references work
  2. T-HP-013 — Run bom_analyzer.py on Audio2LED_PCB/BOM.csv and PCB_legacy/BOM.csv
    • Output: normalized BOM, LCSC alternatives, assembly-ready status
  3. T-HP-033 — Quilter canary route (KiCad -> Quilter -> fab package)
  4. T-HP-035 — kicad-happy playbook parity
  5. T-HP-034 — PCB Designer AI evaluation
  6. T-HP-020 — Forge SPICE review (needs Mistral key)
  7. T-HP-021 — Forge firmware skeleton (needs Mistral key)
  8. T-HP-030/031 — Dataset extraction for fine-tune pipeline
  9. T-HP-022 — Benchmark after fine-tune
  10. T-HP-032 — Post fine-tune evaluation

Key findings from Phase 1 reviews

From the Forge review of 6 DALI PCB sub-schematics:

  • 8 critical issues identified (Zener protection, double ESP32, PCM5122 power, IRF3415 overdim, MCP power chain, MPR121 I2C addr)
  • Cost: ~0.009 EUR for 9 067 tokens — validates the multi-LLM approach for hardware review
  • Next step: BOM analysis (T-HP-013) will cross-reference these findings with component availability and cost