 P1.1 Phase 9 Touch Input (4h)
- TouchEmulator: 4x4 grid navigation via buttons (UP/DOWN/LEFT/RIGHT toggle)
- Files: touch_emulator.{h,cpp} + AmigaUIShell integration
- Button mapping: 0=UP, 1=SELECT, 2=DOWN, 3=MENU, 4=TOGGLE_LR
- Build SUCCESS (31.06s, 64.4% RAM, 42.0% Flash)

 P1.2 Documentation Update (1h)
- AGENT_TODO.md: Phase 9 completion + Sprint 9 section added
- Root cause analysis: watchdog timeout (cycle 9) → stack fix (8192→16384)
- Troubleshooting guide: common issues + debug commands

Files:
  + touch_emulator.{h,cpp}
  ~ ui_amiga_shell.* + main.cpp + AGENT_TODO.md

Next: P1.3 (Sprint 1 endurance validation) + P2 (main.cpp refactor)
2026-03-11 00:03:58 +01:00

8.7 KiB
Raw Blame History

Plan Sprint Applications Zacus

Date de reference: 2026-03-02 Scope: 20 apps declarees dans data/apps/registry.json

1. Strategie de priorisation

Principe:

  • Priorite P0: tout ce qui bloque le parcours utilisateur "launcher -> app -> retour launcher".
  • Priorite P1: apps coeur (utility, capture, audio) utilisables en conditions reelles.
  • Priorite P2: apps kids et NES, une fois la plateforme stable.

Ordre d'execution:

  1. Platforme runtime/launcher
  2. Packs apps par module (pour mutualiser le code)
  3. Hardening, perf, et validation hardware

2. Macro planning (6 sprints)

Hypothese charge: 1 dev principal, 5 jours/sprint.

Sprint 0 (Semaine 1) - Fondations P0

Objectif:

  • Rendre operationnel le flux complet de lancement d'app depuis AmigaUIShell.

Progression (2026-03-02):

  • Bridge launcher/runtime implemente.
  • launchSelectedApp() relie au runtime apps.
  • Anti double-launch (debounce + garde etat running/starting).
  • APP_STATUS serie expose + HELP mis a jour.
  • Logs normalises APP_OPEN_*, APP_CLOSE_*, APP_ACTION_*.
  • LVGL passe en 8.4.x.
  • QR lib pinnee sur commit.
  • tinyexpr ajoute explicitement.
  • [~] ESP32-audioI2S 3.4.4 teste puis rollback en 2.3.0 (incompatibilite <span> avec toolchain actuelle).
  • Gate build pio run -e freenove_esp32s3_full_with_ui verte.

Scope:

  • ui_amiga_shell.cpp: brancher launchSelectedApp() vers APP_OPEN (ou appel direct runtime manager).
  • Navigation launcher: touch + boutons + prevention double launch.
  • Retour propre vers SCENE_READY apres APP_CLOSE.
  • Normalisation logs: APP_OPEN_OK/FAIL, APP_CLOSE_OK/FAIL.

Effort estime:

  • 3 a 4 jh

Risque:

  • Eleve (couplage UI/runtime actuel)

Gate sortie:

  • APP_OPEN audio_player depuis launcher fonctionne.
  • APP_CLOSE ramene sur launcher sans freeze.
  • Build freenove_esp32s3_full_with_ui OK.

Sprint 1 (Semaine 2) - Utility Pack P1

Apps:

  • calculator
  • timer_tools
  • flashlight

Objectif:

  • Finaliser les apps les moins risquées pour valider le pipeline UX.

Progression (2026-03-02):

  • Calculator: tinyexpr actif + erreurs explicites (eval_error@pos) + action status.
  • Timer: actions chrono/countdown stabilisées + action status.
  • Timer: signal fin countdown implémenté (audio/LED opportuniste si ressources disponibles).
  • Flashlight: light_on/off robustes + light_toggle + set_level appliqué à chaud.
  • Script d'endurance et de contrat serial/API ajouté: tests/sprint1_utility_contract.py.
  • Build + flash validés sur cible: pio run -e freenove_esp32s3_full_with_ui puis -t upload.
  • Smoke série court validé: --cycles 5 vert (3 apps).
  • Gate hardware 20 cycles/app à exécuter et archiver (logs + verdict).
    • Essai 2026-03-02: échec à calculator cycle 9/20 avec reboot panic (reset_reason=4).
  • Gate HTTP /api/apps/* à valider (reachability/auth encore instable côté poste de test).

Effort estime:

  • calculator: 1 jh
  • timer_tools: 1.5 jh
  • flashlight: 1 jh
  • integration/tests: 1 jh
  • Total: 4.5 jh

Risque:

  • Faible a moyen

Gate sortie:

  • 3 apps stables sur 20 cycles open/close.
  • Aucune erreur runtime persistante (last_error vide en nominal).

Sprint 2 (Semaine 3) - Capture Pack P1

Apps:

  • camera_video
  • qr_scanner
  • dictaphone

Objectif:

  • Stabiliser camera/micro/filesystem en usage reel.

Progression (2026-03-02):

  • CameraVideoModule: action status + événements normalisés preview/clip/frame.
  • QrScannerModule: action status + alias scan_payload + classification url/app/text.
  • DictaphoneModule: action status + normalisation chemins relatifs (/recorder/...).
  • Harness Sprint 2 ajouté: tests/sprint2_capture_contract.py.
  • Gate série Sprint 2 (1 cycle/app) verte.
    • python3 tests/sprint2_capture_contract.py --mode serial --cycles 1 -> SUCCESS.
  • Endurance courte Sprint 2 (3 cycles/app) verte.
    • python3 tests/sprint2_capture_contract.py --mode serial --cycles 3 -> SUCCESS.
  • Endurance intermédiaire Sprint 2 (10 cycles/app) verte.
    • python3 tests/sprint2_capture_contract.py --mode serial --cycles 10 -> SUCCESS.
  • Déblocage mémoire/coex validé:
    • BOARD_HAS_PSRAM activé (psram_found=1 au boot).
    • tuning runtime: UI_FX_TARGET_FPS=12, UI_DMA_TRANS_BUF_LINES=1, UI_LV_MEM_SIZE_KB=54, ARDUINO_LOOP_STACK_SIZE=16384.
    • fix runtime QR/camera ownership + profil ressource auto (caméra/micro) à louverture app.
  • Gate endurance longue (20 cycles/app) encore à passer pour valider la sortie Sprint 2.

Effort estime:

  • camera_video: 2.5 jh
  • qr_scanner: 1.5 jh
  • dictaphone: 2 jh
  • integration/tests hardware: 1 jh
  • Total: 7 jh

Risque:

  • Eleve (camera + audio + FS + contention)

Gate sortie:

  • Snapshot/photo/record/list/delete valides.
  • Pas de crash sur enchainement camera <-> dictaphone.

Sprint 3 (Semaine 4) - Audio Pack P1

Apps:

  • audio_player
  • audiobook_player
  • kids_webradio
  • kids_podcast
  • kids_music

Objectif:

  • Unifier la stack audio locale/streaming + fallback offline.

Effort estime:

  • audio_player: 2 jh
  • audiobook_player: 2 jh
  • declinaisons kids_media (3 apps): 2 jh
  • integration/tests reseau/offline: 1.5 jh
  • Total: 7.5 jh

Risque:

  • Eleve (Wi-Fi instable, URLs, fallback)

Gate sortie:

  • Streaming fonctionne si Wi-Fi present.
  • Fallback offline automatique si Wi-Fi absent.
  • Reprise audiobook (progress + bookmark) apres reboot.

Sprint 4 (Semaine 5) - Kids Learning/Creative Pack P2

Apps:

  • kids_drawing
  • kids_coloring
  • kids_yoga
  • kids_meditation
  • kids_languages
  • kids_math
  • kids_science
  • kids_geography

Objectif:

  • Finaliser les 2 familles modules: KidsCreativeModule et KidsLearningModule.

Effort estime:

  • base creative (2 apps): 3 jh
  • base learning (6 apps): 4 jh
  • contenus/fixtures progression: 1.5 jh
  • tests endurance: 1 jh
  • Total: 9.5 jh

Risque:

  • Moyen (beaucoup d'apps, logique mutualisee)

Gate sortie:

  • Sauvegarde/reprise validee pour creative + learning.
  • Score/progression lesson persistants pour learning apps.

Sprint 5 (Semaine 6) - NES + Hardening global P2

Apps:

  • nes_emulator

Objectif:

  • Verrouiller la qualite de fin de lot sur les 20 apps.

Effort estime:

  • NES core integration UI/input: 3 jh
  • hardening global (errors, watchdog, retry): 2 jh
  • regression matrix 20 apps: 2 jh
  • Total: 7 jh

Risque:

  • Moyen a eleve (charge CPU/loop timing)

Gate sortie:

  • Validation ROM mapper0 + controls de base.
  • Regression matrix complete verte.

3. Matrice effort/risque par application

App Module Priorite Effort (jh) Risque
audio_player AudioPlayerModule P1 2.0 Eleve
audiobook_player AudiobookModule P1 2.0 Moyen
calculator CalculatorModule P1 1.0 Faible
timer_tools TimerToolsModule P1 1.5 Faible
flashlight FlashlightModule P1 1.0 Faible
camera_video CameraVideoModule P1 2.5 Eleve
qr_scanner QrScannerModule P1 1.5 Moyen
dictaphone DictaphoneModule P1 2.0 Eleve
kids_webradio AudioPlayerModule P1 0.8 Moyen
kids_podcast AudioPlayerModule P1 0.8 Moyen
kids_music AudioPlayerModule P1 0.8 Moyen
kids_drawing KidsCreativeModule P2 1.5 Moyen
kids_coloring KidsCreativeModule P2 1.5 Moyen
kids_yoga KidsLearningModule P2 1.2 Moyen
kids_meditation KidsLearningModule P2 1.2 Moyen
kids_languages KidsLearningModule P2 1.2 Moyen
kids_math KidsLearningModule P2 1.2 Moyen
kids_science KidsLearningModule P2 1.2 Moyen
kids_geography KidsLearningModule P2 1.2 Moyen
nes_emulator NesEmulatorModule P2 3.0 Eleve

4. Risques transverses et mitigation

  1. Couplage launcher/runtime incomplet
  • Mitigation: fermer Sprint 0 avant toute extension app.
  1. Contention camera/audio/LVGL
  • Mitigation: tests de bascule entre apps capture/audio a chaque sprint.
  1. Variabilite Wi-Fi sur apps streaming
  • Mitigation: fallback offline obligatoire et tests en mode deconnecte.
  1. Regression silencieuse des actions app
  • Mitigation: suite smoke serial/API standardisee (APP_OPEN, APP_ACTION, APP_CLOSE).

5. Definition of Done globale

  1. 20/20 apps ouvrables depuis launcher + API.
  2. Chaque app execute au moins 3 actions metier sans erreur critique.
  3. Retour launcher stable apres 50 cycles open/close mixes.
  4. Build firmware + buildfs + upload smoke validates.

6. Execution immediate proposee

Ordre concret des 10 prochains jours:

  1. J1-J2: Sprint 0 (launcher runtime bridge + retour launcher)
  2. J3-J4: Sprint 1 (calculator/timer/flashlight)
  3. J5-J7: Sprint 2 (camera/qr/dictaphone)
  4. J8-J10: Debut Sprint 3 (audio_player + audiobook_player)